News

November 6, 2014 
La Pata Extension Project Update

News ImageConstruction moving Forward. The contractor has made significant progress with the completion of 95% refuse removal at the Prima Deshecha Landfill and 30% of earthwork.


August 1, 2014 
La Pata Extension Project Update

News ImageConstruction of the La Pata Extension Project continues on the La Pata Gap Connector Phase. Clearing and grubbing has been completed and the contractor has completed 50% of refuse removal at the Prima Deshecha Landfill to make room for the new La Pata Avenue. Construction activities for the next six months will include earthwork, drainage improvements, refuse removal, utility relocations, and bridge construction.


July 30, 2014 
Updated Trail Closure Map

News ImageThe trail closure map for the La Pata Extension Project has been updated. The Prima Deshecha Trail will be closed until Fall 2016 at the locations shown on the map. The Forster Ridgeline Trail will remain open to the public. We appreciate your patience and support during construction of the Project.


June 5, 2014 
La Pata Gap Connector Update

News ImageConstruction continues for the La Pata Gap Connector Phase. This phase is expected to be completed in Fall 2016. Below are the details of the project’s construction activities for the upcoming weeks:

REPORTING PERIOD: Monday, June 2 to Friday, June 20, 2014, weekdays, 7 a.m. to 5:30 p.m.


May 5, 2014 
La Pata Gap Connector Phase Begins!

News ImageThe contractor of La Pata Extension Project has begun the construction of the La Pata Gap Connector Phase that will extend the existing La Pata Avenue just south of Vista Montana to Calle Saluda with four new travel lanes for approximately 2.27 miles. The phase is expected to be completed in Fall 2016. Below are the details of the project’s construction activities for the upcoming weeks:
WHEN: May 1 to May 16, 2014, weekdays, 7 a.m. to 5:30 p.m.


view archive »